Corfu, December 23, 2025 – Fraport Greece has initiated the next phase of the Corfu Airport (CFU) terminal expansion project by commissioning The Design Solution (TDS), a UK-based firm, to develop the master plan. This move signifies a progression towards detailed studies, advanced design, and preparation for future construction. However, an official start date for the construction works remains unconfirmed.
Fraport’s Investment Strategy and Project Scope
The terminal expansion is a key component of Fraport’s broader investment strategy for Greek regional airports. The project aims to significantly increase the terminal’s floor area, enhance passenger flow, optimize commercial spaces, and upgrade operational infrastructure. This initiative is expected to bolster the airport’s capacity and improve the overall passenger experience.
The Design Solution’s Role and Project Timeline
TDS’s current mandate focuses on the preparatory and design phases, which are crucial precursors to obtaining final permits, initiating tendering procedures, and selecting contractors. This structured approach means that the completion of studies and securing necessary permits must precede any construction activities. As of now, there is no publicly confirmed timeline for the commencement of construction.
Industry experts suggest that projects of this scale typically involve multiple stages of planning, environmental permitting, and financial structuring. Consequently, it is anticipated that construction works are more likely to begin after 2026, unless Fraport or relevant public authorities issue a specific schedule during 2026. The absence of a concrete timeline underscores the complexity and multi-faceted nature of large-scale infrastructure developments.
Ongoing Infrastructure Upgrades and Runway Works
Independently of the terminal expansion, Corfu Airport is concurrently undergoing an extensive infrastructure upgrade program. This includes critical works on the runway, necessitating partial operational shutdowns. These works are primarily focused on enhancing safety and ensuring compliance with European standards.
A notable aspect of these upgrades is a scheduled full suspension of airport operations from January 12 to January 26, 2026. This two-week shutdown is dedicated to completing essential runway lighting installations, marking the final phase of compliance works. These compliance efforts address recommendations issued by the European Union Aviation Safety Agency (EASA) for airports since 2013, demonstrating a commitment to international safety protocols.
Impact on Airport Operations and Future Outlook
While the runway works will temporarily affect airport operations, they are vital for long-term safety and efficiency. The terminal expansion, once completed, is expected to significantly enhance Corfu Airport’s capabilities, accommodating a larger volume of passengers and improving service quality. The strategic investment by Fraport Greece highlights a commitment to modernizing and expanding key regional aviation hubs.
Further announcements regarding the construction timeline and specific project milestones are awaited from Fraport Greece and the relevant authorities. Stakeholders and the public will be keen to learn about the detailed schedule as the design phase progresses.
Source: GIORGOS KATSAITIS, enimerosi.com